Every new year, homeowners planning a renovation ask us the same thing: has the cost of building work gone up again, and by how much. Here is a straightforward look at where things stand heading into 2026 and how to budget sensibly around it.
Material Costs Are More Stable, But Not Cheap
Timber, insulation and steel prices spiked heavily in 2021 and 2022 and have since settled, but settled at a higher baseline than before, not back to pre-2020 levels. Bathroom and kitchen fittings, particularly anything imported, remain sensitive to exchange rates, so pricing on fixtures can shift between when you first look at a showroom and when you actually order.
Our advice: get fittings priced and, where possible, ordered early in the project rather than assuming the quote you saw six months ago still holds.
Labour Availability Has Eased Slightly
The trade shortages that made it hard to book skilled electricians and plumbers a couple of years ago have eased in the East Midlands, though good tradespeople with strong reputations are still busy well in advance. If you want to start in spring, the time to book your project manager and lead trades is now, not in March.
Realistic 2026 Ballpark Costs
Based on a standard 3 to 4 bed home in Leicestershire and Rutland:
- Full house renovation: £80,000–£190,000+
- Kitchen renovation: £16,000–£48,000
- Bathroom renovation: £7,000–£16,000
- Extension (20 to 30 square metres): £38,000–£70,000+
- Loft conversion: £32,000–£55,000
These are averages, not quotes. Access, finish level and the specific structural challenges of your property will move the number in either direction.
Where to Build in Contingency
We recommend setting aside 10 to 15 percent of your total budget as contingency, particularly on older properties. Once walls are opened up, it is common to find things that were not visible during the survey: old wiring that needs replacing, damp that was hidden behind furniture, or drainage that does not match what was on the original plans. A contingency fund means these discoveries become a manageable adjustment rather than a crisis.
The Real Cost of Cutting Corners on Management
The single biggest cause of budget overruns we see is not material prices, it is poor coordination. A trade turning up before the previous one has finished, materials ordered too late, or decisions delayed until they become urgent, all of these add cost through wasted time rather than the price of the work itself.